CA Crypto Miner to Create 85 Mwh Power Substation

CA Crypto Miner to Create 85 Mwh Power Substation
фото показано с : bitcoints.com

2018-7-27 20:39

DMG Blockchain Solutions Inc., a diversified blockchain company, is in the process of installing an 85-megawatt transformer and electric substation for the company’s cryptocurrency mining facility, according to a company statement.
The new substation is  commissioned to be operational by September 2018, with 60 megawatts available for energizing mining rigs.
The Canadian company offers a range of services including Mining as a Service (MaaS),where it manages bitcoin mining on behalf of third parties at scale.
“DMG is pleased with its progress toward becoming a leading provider of crypto-mining hosting services in North America,” said Reitzik.
EVP for Corporate Development Steven Eliscu added that the combination of “leading-edge mining equipment and access to low-cost power” makes him “optimistic” about the future of the company.

Similar to Notcoin - TapSwap on Solana Airdrops In 2024

origin »

High Performance Blockchain (HPB) на Currencies.ru

$ 0.0100291 (+7.61%)
Объем 24H $25.057k
Изменеия 24h: 5.20 %, 7d: 30.40 %
Cегодня L: $0.0090557 - H: $0.0100291
Капитализация $732.823k Rank 1812
Цена в час новости $ 2.00457 (-99.5%)

company substation mining blockchain facility statement new

company substation → Результатов: 1